The SI Government has confirmed that the Solomon Islands National Broadband Infrastructure Project or SINBIP for the construction of up to 161 towers has been progressed with the recent signing of a contracting agreement with the vendor and contractor, Huawei/China Harbour Engineering Company Limited.
A joint statement from the Ministry of Finance and Treasury and the Ministry of Communication and Aviation confirmed that a formal due diligence process and steps within the overall Government’s Procurement guidelines are followed to the execution of the contract.
The SINBIP is one of the priority projects of the National Government. The SINBIP is consistent not only with the DCGA Policy Statement, but is also in line with the Solomon Islands National Infrastructure Investment Plan (2013), National ICT Policy (2015), and Solomon Islands National Development Strategy, 2016-2035 (2016).
Work on the SINBIP started in 2019 with the submission of a feasibility study on the project. After a cabinet endorsement then, a Steering Committee was set up, consisting of senior staff from relevant government ministries, to review the SINBIP feasibility proposal put forward by Huawei and advice Cabinet not only on its financial and economic viability, but also on its technical compatibility with the country’s existing telecommunication infrastructure.
As a result, the Steering Committee contracted a local expert and a private consulting firm from New Zealand, with both financial and technical expertise to provide an independent review of the SINBIP feasibility study. The two consultant’s recommendation revealed that the SINBIP is both financially viable and compatible with existing telecommunication infrastructure in the country.
In terms of funding, the statement confirms that the SINBIP will be fully funded with a 20 years’ term concessional loan of approximately CNY448.9 million from the Exim Bank of China at one percent (1.0%) interest rate.
This proposal will be a historical financial partnership with the Peoples Republic of China (PRC) since the two countries established diplomatic ties in 2019 as the two countries work closely to ensure the successful implementation and operation of the project.
The independent review of the SINBIP showed that the project would generate sufficient revenues for Government to fully repay both the principle loan amount and interest costs within the loan period.
It was further confirmed that the proposed mobile towers are very important aspects of the country’s telecommunication infrastructure assets. As such, government plans to create a new company, as owner of the infrastructures on behalf of the Government. This is similar to the arrangement where government has created a new company, called Solomon Islands Airport Corporation Ltd (SIACL) or the Solomon Islands Cable Company Limited (SICCL).
In terms of the operation of the towers, the committee is holding ongoing discussions with Solomon Telekom Company Limited (STCL) as a key operating partner. The SINBIP system will be connected to the STCL core network throughout the country. In this regard, the SINBIP will result in the further expansion of the STCL network. This will provide a better telecommunication coverage for our people and businesses throughout the country. The proposed arrangement will also provide a clear level playing to other operators like the Bemobile company services throughout the country.
The government also confirmed that although it has already signed the Contract with the vendor and the contractor for the construction and supply of all tower equipment, the next step will be subjected to a formal Memorandum of Operation Agreement (MoA) with STCL and on the final funding agreement between the SIG and the EXIM Bank of China.
The Government hopes to finalised these outstanding requirements before the end of this year to allow construction to commence in early 2023.
The government expects to complete the first 48 percent of the 161 towers before the Pacific Games in November 2023. This should enable people, especially in the rural areas, to enjoy the games even if they do not come to Honiara.
It was also confirmed that one of the key criteria towards the selection of the proposed tower sites include no co-location of existing STCL and Bemobile towers and to the unserved public services institutions like schools and rural health centers, as well as to areas of potential economic activities.
The proposed investment will utilize services or capacity currently provided by the Undersea Cable investments.